Roadworks zones NSW

myp

Active Member
:(:confused::(:confused:
Lately we've had a lot of roadworks around our area with 40k signs etc. and as usual no end of works sign.

Spoke to stop/go person about it at one site and she said they were in a hurry and forgot them as they were running late.:(:(:(:(

So the age old question is it a requirement by law or not? If it is who polices it? What happens about the speed you are required to travel at, when does it end?

The hunt for the answers begins first stop the police. Their response "Good questions, but honestly we do not know." "We suggest you try the RTA."

Tried the RTA. No luck, put me on to their legal people still nothing suggested I try the minister or local member. Back to the RTA Traffic Management Dept. took name and number and was told somone will ring.

HMMMMMMM!!!!!:mad::mad::mad::mad:

I ended finding out by ringing the company initially concerned, and they were quite helpful and very informative. The lady on the other end could even tell me what day and time it was and the lollypop person I spoke to.:D:D:D AT LAST!!!

For all of you wondering and cursing drivers, at least in NSW anyway, here's what she told me;
Firstly it is a legal requirement if there is a "roadwork begins" sign (the mound of dirt and a shovel) then there must be a "roadwork ends" sign.

Secondly if there is a sign saying "roadwork speed limit enforced" with a speed limit eg 40kph you must reduce to that speed. All other speed signs in the work zone MUST be covered.

Thirdly and this the on that gets me. If there is no "roadwork speed enforced" sign or the other speed signs are not covered then you are allowed to travel at the normal posted speed for that road and cannot be booked.

So that says the next time you are driving down the expressway and come upon roadworks with a speed limit and a little up the road there is a sign showing 110k then you're allowed to speed up, even though you're clearly still in the works zone.:(:(

THAT'S BLOODY RIDICULOUS!!!!!! What about everyones safety????

Lastly she told me that she has two teams that go out every day to each site to make sure all the signs are in place.

I have been a professional driver for 23 years and driven around 8 million ks. I have always slowed at work sites, for joggers, cyclists even giving them a beep of the horn, just to let then know I'm there and where possible move over to go past.

Martin
Have a good day

ps The lady Ispoke to owns the traffic control company.
 

Vegetoast

Active Member
Mate I wouldnt listen to her, she told you some bad ones, I've have to do 4 traffic control courses every 4 years to do my job and I very very rarely use a slow bat. I've been in control of mobile works, intermittent and short term works for more than ten years, If you want information you'll want to get it for the traffic control trainers, you could give coats hire a call they do training.

End of roadworks sign is only required at long term sites.
Roadwork speed limit enforced sign is complimentary to remind drivers.
If in a reduced speed zone you noticed they didnt cover a sign and you obviously still in a work site well then brainless TC most likely didnt cover it cause a txt on his phone was more important to him at the time and forgot, its common sense to still do the reduced speed limit, of course you'd win in court for picking up your speed but what about the safety of the workers there that have nothing to do with the traffic control.

If you pick up speed approching the end of works 110 signs you can still be booked, you must pass the sign.

I cant type anymore, I have to go to work now.. hope that clears something up.
I thought I told you what I did for a living.
 

myp

Active Member
Hj Jon,

Please don't take what I wrote as what I would do. I know first hand the risks of being on the side of the road with vehicles going past @ 100ks or more. its what Iwas told by supposedly the owner of a local traffic control business.
I found some of what she said incredulous and I fully agree with you about safety for EVERYONE not just the workers.

But on the other side of the story. Why dosen't anybody including the legal team know what the correct answers.

I wrote what I did because I didn't believe what I heard and was hoping, correctly as it turns out, someone out there would probably have the right answer.

So Jon am I right if its eg posted as a 40 work zone and there is no end of work sign then it is a matter of common sense as to when you reapproach the road limit?
 

03hilux

4x4 Earth Contributer
When i drive through a works zone, i always slow to the zones speed limit even on sundays when most site are dormant. You never know what will jump out at you.
If there is no "end road work" sign,and the normal speed limit is between 60 and 80km/h, i'll drive about 100 mtrs past the last witches hat before speeding up. Anything over 80km/h, and i'll go 400-500 before i speed up.
 

Vegetoast

Active Member
Hj Jon,

Please don't take what I wrote as what I would do. I know first hand the risks of being on the side of the road with vehicles going past @ 100ks or more. its what Iwas told by supposedly the owner of a local traffic control business.
I found some of what she said incredulous and I fully agree with you about safety for EVERYONE not just the workers.

But on the other side of the story. Why dosen't anybody including the legal team know what the correct answers.

I wrote what I did because I didn't believe what I heard and was hoping, correctly as it turns out, someone out there would probably have the right answer.

So Jon am I right if its eg posted as a 40 work zone and there is no end of work sign then it is a matter of common sense as to when you reapproach the road limit?

If you havent passed another speed sign since the last 40 then the speed limit is still legally 40 until the next posted speed sign, end of works sign should be mandatory.

Something else she said thats wrong, The digger sign (mound of dirt and shovel) means there are workers on the road, and comes after the first sign Road works ahead or can be used by itself for short term works under 30min. does not require End of road works sign. A speed reduction means workers or machinery may be working next to the hats/bollards/gurseys(or other form of delineation) or the lanes are narrower than 3m in the worksite. Private roads like the M7 have their own variants to the rules too.

Mobile works doesnt require posted signs, just trucks with arrow boards.

You'll find on most sites that only 1 or 2 people have all the tickets for traffic control and the rest only have the basic 2 and are "trying" to follow their simple instructions.

Who polices it? The RTA or RMS, OH&S and contracted inspectors, on average the RTA audits me 3 times a year and inspectors once a month but have never seen OH&S.

Non of the groups you called know the answers because they dont practice it. The police have their own rules and the RTA is huge your best chance would be to call one of their roadworks depo as there should be some TC's there.
Also the TC rules are changed all the time and everyone has to keep repeating all the courses for their tickets they have, not cheap either its costing me including loss of pay to do them around the 3 grand mark for all 4 courses.

I got my first TC ticket for $80 20 years ago and it was suppose to be for life. I got roughted.

When I got my drivers license , flashing amber lights ment your suppose to halve your speed and drive with caution... dont know what happen to that..
Not pointing the finger at anyone here but what I've noticed is that the road is everyones open race track and us workers are just in the way. They dont teach people how to drive on our roads anymore, they only teach how to get a licence. And courtesy on the road is 1 in a couple of thousand and declining.

Hope that helps, sorry for the rant but I could go on and on.

Oh yeah watch out for me. Mobile work site, no signs or speed reduction just 2 plant trucks with arrow boards (in some language that nobody understands) in the middle of the road and we're not a mobile slalom unit as alot of people seem to think, we do seem to be a good target for eggs, rocks, bottles and even had a brick thrown at me from a van doing 80+kmh.
 

LowLux

Moderator
You can look up AS1742.3 (Aust Standards 1742.3) and the DTEI for regulations and laws regarding road traffic management and control systems. All Medium and Long Term road works must have a traffic management plan drawn up, including diagrams of the site and signage on site and they must meet AS1742.3, they must also be adhered to for the duration of the works. In the situation whereby signage is altered, the plans must be modified to reflect those alterations asap. If there is signage missing or incorrect signage in place and an accident was to happen due to that, someone would be in the poop, big time! with potentially big fines!
 
Last edited:

Vegetoast

Active Member
You can look up AS1742.3 (Aust Standards 1742.3) and the DTEI for regulations and laws regarding road traffic management and control systems. All Medium and Long Term road works must have a traffic management plan drawn up, including diagrams of the site and signage on site and they must meet AS1742.3, they must also be adhered to for the duration of the works. In the situation whereby signage is altered, the plans must be modified to reflect those alterations asap. If there is signage missing or incorrect signage in place and an accident was to happen due to that, someone would be in the poop, big time! with potentially big fines!

Thats the supposedly Australian standard for traffic control system devices.
There's no Australian standard in the practice of traffic control, its managed differently state for state. Even the road rules, linemarking and vehicle standards are different.
And yes if the site doesnt comply with the TCP on any term site and an acco happen's it can be very costly for the supervisor's, companies involved and the owners. Its not pinned on one person, in NSW anyway.
Even running mobile works I have to carry multiple TCP's(as simple as they may be) amongst other detailed paperwork for everything we do and use to fill in.
 

myp

Active Member
Thanks Jon, why the rta couldn't direct me to that doco I don't know.
If I'm reading this right then if there is a roadworks ahead sign there must be a end roadworks sign.
and if there if a 40k or other speed reduced limit sign sign then at the end of the works there must be the normal sign to indicate the end of works.

Thanks again Martin
 

Vegetoast

Active Member
Thanks Jon, why the rta couldn't direct me to that doco I don't know.
If I'm reading this right then if there is a roadworks ahead sign there must be a end roadworks sign.
and if there if a 40k or other speed reduced limit sign sign then at the end of the works there must be the normal sign to indicate the end of works.

Thanks again Martin

You have read it right Martin (correct for the site I believe your talking about), But I think you might need to read on a bit more though if your interested. They could have some short term works within or around that long term site.
Roadworks ahead sign can still be used on short term site's without the end of works sign.and yes the speed limit should be restored.
If you come across a site you believe is dangerous or just confusing, you can call the Traffic management center (TMC) 0283961686 and get it checked out, Not only do the traffic controllers have to follow a TC plan that fits the road and Job but it also has to fit in with the regulation of the road occupancy licence that the TMC have approved and if the site is confusing I very doubt the traffic control has a plan that suits.
Only hope I havent confused you more...lol
 